nrc seal Weekly Information Report

For the Week Ending September 24, 1999

[ archive ]

The Weekly Information Report is compiled by the NRC Office of the Executive Director for Operations and includes highlights of Headquarters and Regional Office activities. For technical questions, please contact J. Yerokun, OEDO by E-mail: jty@nrc.gov. For administrative questions, please contact Patricia Anderson at (301) 415-1703, or by E-mail: paa@nrc.gov. If you would like to request a hard copy, you may contact the NRC Public Document Room at (202) 634-3273, or by E-mail: mailto:pdr@nrc.gov


Contents


The following offices had No information for this issue:


Office of Nuclear Reactor Regulation

[ Prev | Next ]

Maine Yankee

On September 15, 1999, Maine Yankee filed suit in U.S. District Court in Portland, Maine, against the State of Maine regarding the role that the State proposes to take in the licensing of the MY ISFSI. The suit stems from the August 19, 1999, decision by the State Board of Environment Protection (BEP) to assert jurisdiction on MY's plans to store fuel in an onsite ISFSI. The State is offering an opportunity for a public Hearing under its site permitting authority.

Maine Yankee intends to construct the ISFSI under the general license provisions of 10 CFR Part 50 in what is now a parking lot near the low level waste storage building. The licensee is planning to use the NAC International (NAC) Universal Multi-Purpose Canister System (UMS) for storage of its fuel and greater-than-class-C waste consisting of irradiated core internals. The licensee intends to build eight concrete pads on which it will store up to 66 UMS casks (60 for spent fuel and six for greater-than-class-C waste). Fuel movement from the spent fuel pool would begin in the spring of 2001 and be completed by the fall of 2002.

Cooper Nuclear Station - Loss of Zulu Sump Pumps

On September 17, 1999, after 271 consecutive days of operation, Cooper Nuclear Station (CNS) experienced a loss of the Zulu sump pumps and subsequently both trains of the Standby Gas Treatment (SGT) system were declared inoperable. The plant was shut down and placed in MODE 4 to comply with CNS Technical Specifications (TS). Subsequent inspections and evaluations determined that the plant sustained a hydrogen explosion within the offgas system sometime earlier in the day. The hydrogen explosion was contained within the system, but the Zulu sump sustained some damage. The sump is part of the offgas system and secondary containment. It was reported on September 22, 1999, that repairs to damaged equipment have been completed and final preparations were continuing in order to support plant startup. The final root cause investigation results and damage extent report are scheduled to be reviewed by CNS's Site Operations Review Committee (SORC) prior to plant startup which is tentatively scheduled for the afternoon of September 22, 1999.

Fire Protection Pilot Baseline Inspection Meeting

On September 13-15, 1999, the Office of Nuclear Reactor Regulation conducted an NRC

Fire Protection Pilot Baseline Inspections Counterpart Meeting and a Fire Protection Pilot Baseline Inspection Licensee Pre-brief Meeting at the Holiday Inn Bethesda. On September 13 and 14, 1999, managers and inspectors from the NRC regional offices attended the Counterpart Meeting, as did various cognizant individuals from the New Reactor Oversight Program, TTD, RES, and Sandia National Laboratory (inspection contractor). The topics for which formal talks were delivered were Fire Protection Functional Inspection (FPFI) program results and their significance, an overview of the New Reactor Oversight Program, and the structure, content and conduct process of the current draft fire protection baseline inspection procedure. Discussions were held regarding baseline program inspection staff resources and inspection scheduling, as well as the information gathering and inspection plan preparation activities of the baseline triennial fire protection inspection teams. Detailed training was conducted on the development and application of the Fire Protection (findings) Risk Significance Screening Methodology (FPRSSM), part of the Oversight Program's Significance Determination Process (SDP). Use of FPRSSM results to both focus onsite fire protection inspection activities and characterize fire protection findings was also discussed.

Pilot fire protection baseline inspections will be conducted at Salem, Harris, and Ft. Calhoun over the next 4 months. On September 15, 1999, managers and inspectors from the NRC regional offices attended the Licensee Pre-Brief Meeting for the Salem, Harris and Ft. Calhoun licensees, as did various cognizant individuals from the New Reactor Oversight Program, TTD, RES, and Sandia National Laboratory. In addition, representatives from the pilot licensee organizations and interested members of the public and industry attended (including representatives of the State of New Jersey, the Nuclear Energy Institute (NEI), and the Boiling Water Reactor Owners Group (BWROG)). Topics for which formal talks were delivered were FPFI program results and their significance, an overview of the New Reactor Oversight Program, and the structure, content and conduct process of the current draft fire protection baseline inspection procedure. The Fire Protection (findings) Risk Significance Screening Methodology (FPRSSM), part of the Oversight Program's Significance Determination Process (SDP), was reviewed. Use of FPRSSM results to both focus onsite fire protection inspection activities and characterize fire protection findings was also discussed.

Nuclear Energy Institute (NEI) Workshop

On September 13, 1999, NRC staff from the Office of Nuclear Reactor Regulation (NRR) participated in a Nuclear Energy Institute (NEI) workshop on industry guidance for implementing the 10 CFR 50.65 (the maintenance rule) (a)(4) revision, which will require licensees to assess and manage the increases in risk resulting from maintenance activities and provides an option for a risk-informed reduction in assessment scope. Roy Zimmerman, Deputy Director of NRR, spoke on the "New Regulatory Direction." Richard Correia, Chief of the Reliability and Maintenance Section, presented the staff's "Perspective on the NEI Guidelines to Implement 10 CFR 50.65(a)(4)." Doug Coe, Senior Reactor Analyst from the Division of System Safety and Analysis, discussed the new "Significance Determination Process." Frank Gillespie, Deputy Director of the Division of Inspection Program Management, was scheduled to speak, but the second day of the conference was canceled due to the arrival of Hurricane Floyd. Peter Balmain, Wayne Scott, Frank Talbot, and See-Meng Wong were also participants.

National Organization of Test, Research and Training Reactors (TRTR) - Annual Meeting

The annual Meeting of TRTR was held at the National Institute of Standards and Technology on September 15 - 17, 1999. September 15 was NRC day with the day devoted to presentations from the NRC staff. The opening address was given by the Chairman and the EDO was the Keynote speaker after lunch. Commissioner Diaz was the speaker at the Thursday evening dinner. Presentations were given on topics such as an overview of the NPR regulatory program, regulatory issues since the last TRTR Meeting, radioactive material transfer issues, operator licensing results, Senior Reactor Operators limited to fuel handling, decommissioning issues, license renewal, changes to 10 CFR 50.59, transportation of radioactive material issues, and an overview of ADAMS. There were breakout sessions with NRC staff and management to allow small group discussions on items of interest with licensees.

In general, the TRTR community believes the NRC's regulatory approach towards NPRs is appropriate, however, some concerns were raised by licensees. These concerns were primarily that the changes, initiatives and new processes in the power reactor area such as the move towards risk informed regulation would be applied to NPRs without careful consideration. The NRC staff assured licensees that they would be aware of these concerns as these issues developed.

Restart of Brunswick and Pilgrim after Hurricane Floyd

The Emergency Preparedness and Health Physics Section (IOLB/DIPM) served as the main NRR contact with FEMA to ensure that the restart of the Brunswick and Pilgrim plants following Hurricane Floyd were coordinated with FEMA's affirmation of the adequacy of offsite emergency preparedness in the Emergency Planning Zones of these facilities. The EP&HP staff followed the communication protocol referred to in the memorandum on plant restarts after natural disasters issued on May 24, 1999, from Bruce Boger, Director/DIPM, to the DRS Regional Directors. The communication protocol is documented in Inspection Manual Chapter 1601 and Administrative letter 97-03 and was developed in response to lessons learned following Hurricane Andrew in 1992 and other more recent events. In anticipation of the hurricane reaching land, the EP&HP staff brought the May 24, 1999, memorandum and communication protocol to the attention of key NRC staff in the Regions and Projects, and established points of contact with FEMA representatives and others as necessary for communications especially during off-hours.

In general, the coordination between NRR, the Regions, and FEMA was excellent. The staff maintained contact with the Region Duty Officers and with personnel in the Region Incident Response Centers. Communications with the FEMA assessment teams and local support agencies were also coordinated to assure current and accurate information. The staff also maintained and provided status reports to NRR management as well as to the Incidence Response Operations Center. This effort required considerable off-hours and late night communications for which special mention is made of the service provided by Larry Cohen of the EP&HP staff who handled most of the off-hours activities. Excellent team work and good communications between all parties in accordance with the established protocol resulted in timely and effective decision making allowing the licensees to restart their facilities while at the same Time providing assurance to the public that adequate offsite emergency response was being maintained.


Office of Nuclear Material Safety and Safeguards

[ Prev | Next ]

First Public Meeting on Control of Solid Materials

On September 15-16, 1999, the first of four facilitated public meetings to discuss issues and alternatives related to control of solid materials at licensed facilities was held in San Francisco, California. Attendance at the Meeting included representatives from licensees and licensee organizations, the Health Physics Society, Environmental Protection Agency, Department of Energy, state agencies, scrap and recycling companies, steel manufacturers, sanitary waste facilities, a newspaper, and Indian tribes. There were No representatives from citizen groups, however a letter from 12 citizen groups explaining why they did not attend was delivered to the Meeting and copies were provided to attendees.

The Meeting agenda consisted of multiple sessions corresponding to the content of the Issues Paper. One session focused on the need for a national standard for control of solid materials and the process currently being used, and included a discussion on ways to enhance public input to include community meetings. Another session focused on the types of materials and licensees, potential radiation doses, and efforts of other federal, state, and international agencies and organizations, and included a discussion on the need to consider naturally occurring and accelerator produced material as well as mixed waste issues. A third session included a discussion about state, local, and tribal authorities and associated constraints. Following a discussion of the Nuclear Regulatory Commission's current approach for handling control of solid materials, several potential alternatives for addressing this issue were discussed. The alternatives identified in the Issues Paper included: (1) continue current approach; (2) allow unrestricted use; (3) allow restricted use; and (4) prohibition. Other alternatives discussed were: (1) adopt the ANSI standard; (2) combine restricted/unrestricted use option to allow flexibility; (3) adopt material-specific controls; (4) use general licensing; (5) use an interim storage facility; (6) have a buy-back program of contaminated materials during first use processing; and (7) guarantee that a dedicated steel mill is not responsible for financial losses if contamination occurs at the mill from the material received. There were extensive discussions on the potential health and environmental impacts to be considered in addition to the potential economic and cost-benefit considerations. The last session focused on implementation aspects to ensure control of solid materials under various alternatives. There was general consensus among the participants that measurement and implementation methods are essential, but will be difficult to develop.

The discussions provided useful information which the staff will use as part of developing a paper for the Commission in March 2000.

Meeting with Energy Northwest on Dry Spent Fuel Storage Plans

On September 20, 1999, Spent Fuel Project Office staff met with representatives of Energy Northwest to discuss their plans for dry spent fuel storage at the WNP-2 plant. Energy Northwest plans to use the general license provisions of 10 CFR Part 72, and anticipates beginning to load storage casks in January 2002, using the Holtec International HI-STORM storage system.

International Atomic Energy Agency Monitoring of Alternate Nuclear Materials

In November 1998, the International Atomic Energy Agency (IAEA) Secretariat requested approval from the IAEA Board of Governors for the authorization to collect and evaluate information on neptunium and americium (often referred to as "Alternate Nuclear Material" (ANM)) to determine if, or when, the ANMs become a proliferation concern. Consensus approval of the proposal has been blocked for 10 months because of disagreements on the concepts within the five nuclear weapon states. Following frequent meetings at the ambassador level in Vienna during the summer, the weapons states reached agreement on the text of the Board of Governors statement on September 13, 1999. On September 20, 1999, the IAEA Secretariat proposal for monitoring the ANMs was approved by the Board of Governors.

International Safeguards of Highly Enriched Uranium Down-blending at BWX Technologies

On September 16-17, 1999, Division of Fuel Cycle Safety and Safeguards (FCSS) staff facilitated a planning Meeting between the International Atomic Energy Agency (IAEA) and BWX Technologies regarding the implementation of IAEA safeguards measures on the highly enriched uranium (HEU) down-blending system. The facility operator provided the IAEA with the most recent design information on the facility. The down-blending units have been installed. However, before installing the inter-unit connectors, the facility operators wanted to ensure that the IAEA safeguards equipment could be effectively installed in the inter-unit space provided. The operator and IAEA discussed the process for implementing the IAEA safeguards measures and resolved schedules and implementation details necessary for IAEA safeguards to be implemented when downblending begins in November. The FCSS staff identified several potential enhancements to the proposed safeguards approach that would facilitate the implementation of the IAEA's safeguards goals and would ensure that the U.S. non-proliferation policy goals associated with the HEU down-blending project would be met. The IAEA Secretariat is currently considering the FCSS staff suggested enhancements.

Congressional Hearing on Paducah Gaseous Diffusion Plant

On September 22, 1999, Nuclear Regulatory Commission (NRC) staff provided testimony at a Hearing held by the House Commerce Committee, Subcommittee on Oversight and Investigations. The Hearing focused on contamination and worker safety issues at the Paducah site. Most of the testimony and Congressional questions concerned events which took Place under Department of Energy (DOE) regulatory oversight and during the Time when DOE processed recycled uranium through the facility. These events took Place from about 1955 to about 1975, before NRC assumed regulatory oversight of the portion of the site leased by the U.S. Enrichment Corporation (USEC). NRC answered questions on USEC worker safety and contamination on USEC leased areas, USEC's enforcement history and progress in implementing seismic modifications to the C-335 and C-331 buildings at the Paducah site.


Office of Nuclear Regulatory Research

[ Prev | Next ]

Research Task Force Meeting on Radiation Materials Science Applied to Reactor Pressure Vessel Embrittlement

On September 20-22, 1999, the DOE, NRC, and EPRI co-sponsored a Meeting in Charleston, South Carolina, concerning techniques of radiation materials science that have been, or could be, applied to understand, characterize, and predict embrittlement in nuclear reactor pressure vessels. Attendees at the Meeting included staff from DOE, NRC's RES and NRR, EPRI, and many of the contractors who conduct research for these organizations. The presentations highlighted research needs to support current plant operation, license renewal, and new plant designs. Additionally, on-going work on these three areas, both basic and applied, was discussed. Meetings of this type are held regularly to help identify and prioritize research project topics.

At the Meeting, RES/DET staff discussed the possibility of obtaining reactor pressure vessel (RPV) steel from a decommissioned commercial reactor (Maine Yankee) for testing. Testing of such materials will provide key insights regarding conservatism inherent to procedures for assessing the safety of nuclear RPVs still in operation, and could provide opportunities to reduce unnecessary licensee burden. Representatives from EPRI and DOE both expressed support for this idea. RES continues to work with EPRI and DOE to secure samples for testing, and to obtain financial support.


Incident Response Operations

[ Prev | Next ]

Chemical Emergency Preparedness Conference

A staff member from IRO was a featured speaker at the EPA, Region III Chemical Emergency Preparedness Conference held on September 20-23, 1999 at the Washington Hilton. His talk was on the Integration of the Federal Radiological Emergency Response Plan and the National Contingency Plan. Participating as co-speakers on this Subject was a representative from the Department of Energy and from EPA, Region III. EPA, Region III, and NRC conducted a Lost Source Exercise (Nureg-1634) in 1997, which explored the relationship between the two plans. A discussion of that exercise was included in the presentation. This EPA, Region III, conference is one of the largest of its kind in the United States. Over 1500 emergency responders attended with a focus on chemical and oil spill response. This was the first Time radiological materials response has been on the agenda.

Preliminary Notifications:

1. PNO-III-99-042, United States Enrichment Corporation, RUPTURE OF A LARGE SANITARY WATER LINE

2. PNO-IV-99-039, Team Consultants, STOLEN PORTABLE MOISTURE/DENSITY GAUGE


Office of Administration

[ Prev | Next ]

Procurement Reform

On September 23, 1999, representatives from the Division of Contracts and Property Management (DCPM) and the Office of the Chief Financial Officer (OCFO) met with the Industry Advisory Council (IAC) Procurement Reform Task Force to discuss NRC IT acquisition reform success stories. DCPM and OCFO representatives discussed NRC's streamlined acquisition of commercial software to upgrade the NRC's payroll, Time and labor, and human resources software module. In addition to this project, the group discussed various other NRC initiatives that have been implemented as a result of the NRC's Procurement Reinvention Laboratory, the Federal Acquisition Streamlining Act and the Clinger-Cohen Act.

The IA representatives indicated that they planned to recommend NRC's examples for highlighting to other agencies for procurement best practices.

State of Nevada; Receipt of Petition for Rulemaking (PRM-73-10)

A document that requests public comment on a petition for rulemaking submitted by the State of Nevada was published in the Federal Register on September 13, 1999 (64 FR 49410). The petitioner requests that the NRC amend its regulations governing safeguards for shipments of spent nuclear fuel against sabotage and terrorism. The petition requests that the NRC conduct a comprehensive assessment of the consequences of specific types of terrorist attacks and modify its regulations accordingly. The comment period for this action closes November 29, 1999.

Proposed Compatibility Designation Change and Draft Emplacement Criticality Guidance for Low-Level Waste (Part 61)

A document requesting public comment on whether the criticality designation of the provision in the Commission's regulations that requires low-level waste disposal facility licensees who receive and possess special nuclear material to describe proposed procedures to avoid accidental criticality of these wastes before disposal and after disposal in the ground was published in the Federal Register on September 20, 1999 (64 FR 50778). The document also requests comment on draft guidance on emplacement criticality at low-level waste disposal facilities. The comment period for this action closes October 20, 1999.

List of Approved Spent Fuel Storage Casks: (VSC-24) Revision (Part 72)

A direct final rule that revises the Pacific Sierra Nuclear Associates VSC-24 cask system listing within the list of approved spent fuel storage casks was published in the Federal Register on September 22, 1999 (64 FR 51187). The amendment modifies the present cask system design to permit a licensee to store burnable poison assemblies along with the spent fuel under a general license. The final rule becomes effective December 6, 1999.

The companion proposed rule to this direct final rule was published in the Federal Register on September 22, 1999 (64 FR 51187). The comment period closes October 22, 1999.

List of Approved Spent Fuel Storage Casks: (Holtec HI-STORM 100) Addition (Part 72)

A proposed rule that would add the Holtec International HI-STORM 100 cask system to the list of approved spent fuel storage casks was published in the Federal Register on September 22, 1999 (64 FR 51271). The amendment would allow holders of nuclear power plant operating licenses to store spent fuel in the TN-68 cask system under a general license. The comment period for this action closes December 6, 1999.

Industry Codes and Standards; Amended Requirements (Part 50)

A final rule that amends the regulations that incorporate by reference industry codes and standards was published in the Federal Register on September 22, 1999 (64 FR 51370). The final rule incorporates by reference more recent editions and addenda of the ASME Boiler and Pressure Vessel Code and the ASME Code for Operations and Maintenance The final rule becomes effective November 22, 1999.


Chief Information Officer

[ Prev | Next ]

Freedom of Information and Privacy Act Requests received during the 5-Day Period of September 17, 1999 through September 23, 1999:

Stone & Webster Engineering Corp., documents submitted regarding large and small bore piping,, or submitted by the identified licensees. (FOIA/PA 99-364)

Contract, RS-ADM-00-004. (FOIA/PA 99-365)

MLTS database. (FOIA/PA 99-366)

Shearon Harris plant, CP&L licensee, spent fuel pools, heat loads and/or heat production calculations, heat removal. (FOIA/PA 99-367)

White Mesa uranium milling facility, San Juan County, UT, license SUA-1358 re ground water. (FOIA/PA 99-368)

Site suitability safety report, 1977 Dames & Moore, Perryman plant, Baltimore Gas & Electric, seismic-reflection data. (FOIA/PA 99-369)

Mailing list for NRC publications. (FOIA/PA 99-370)


Office of Human Resources

[ Prev | Next ]

Arrivals
CAVALLO, Laura RESOURCE MANAGEMENT ASSISTANT RIV
WILLNER, Mary A. HUMAN RESOURCES SPECIALIST (RECRUIT) HR
JASKINSKI, Robert PUBLIC AFFAIRS OFFICER OPA
Retirements
BAILEY, Ronald M. REACTOR ENGINEER RIII
COLLINS, Joyce SECRETARY NMSS
POURCHOT, George AUDIT MANAGER OIG
Departures
BUTLER, David S. REACTOR ENGINEER RIII
HANSEN, Jeffery L. RESIDENT INSPECTOR RIII

Office of Public Affairs

[ Prev | Next ]

Media Interest

The television show "60 minutes" inquired about depleted uranium and its use in the Gulf War.

Press Releases
Headquarters:
99-200 Note to Editors: ACRS Meeting postponed
99-201 NRC Advisory Committee on Reactor Safeguards to Meet in Rockville, Maryland
99-202 NRC Issues Final Revisions to Regulations on Respiratory Protection
99-203 NRC Revises its Regulations for Making Changes to Licensed Facilities
Regions:
I-99-83 Note to Editors: New Date Set for Meeting on Indian Point 2 Inspection

Office of International Programs

[ Prev | Next ]

Visit by Electricite de France

On September 24, 1999 Mr. Francois Roussely, Chairman of Electricite de France (EdF) visited the Commission. He was accompanied by Jacques Chauvin, EdF Executive Vice President and Chief Financial Officer, Jean-Remy Cauquil, Advisor to the Chairman for International Affairs, and Jean Cottave, President of EdF International North America Inc.

Mr. Roussely became EdF Chairman in July 1998, and used this opportunity to introduce himself to the Commission. He was particularly interested in the NRC's actions in life extension and license renewal, decommissioning, foreign ownership of nuclear facilities located in the U.S., and the future of nuclear power and regulation in the U.S. Mr. Roussely also discussed the European Pressurized Water Reactor (EPR), an evolutionary, 1500 Mwe PWR being developed by Framatome of France and Siemens of Germany. The basic design phase has been completed and an optimization phase is underway, and EdF, Framatome and Siemens are developing a joint organization to engineer the plant. The respective regulatory authorities have agreed on a set of common safety guidelines.


Office of the Secretary

[ Prev | Next ]

Document Released

to Public

Date Subject
Decision Documents
1. SECY-99-214 8/23/99 Options for Proceeding with NRC's Efforts Regarding the Release of Solid Materials
SRM on 99-214 9/20/99 (same)
Commission Voting Record on 99-214 9/20/99 (same)
Information Papers
1. SECY-99-224 9/8/99 Weekly Information Report - Week Ending September 3, 1999
Memoranda
1. M990924 9/24/99 Affirmation Session, September 24, 1999, SECY-99-236 - First Energy Nuclear Operating Co., et al. (Beaver Valley Power Station, Units 1 and 2), Docket Nos. 50-334-LT and 50-412-LT, Local 29's Petition to Waive Time Limits in 10 CFR 2.1305 and Supplemental Comments

Commission Correspondence

1. Letter to David A Lochbaum, Union of concerned Scientists, dated September 17, 1999, concerns July 1, 1999 revisions to the 10 CFR 2.206 petition review process documented in Management Directive 8 11 (MD 8 11), "Review Process for 10 CFR 2.206 Petitions."

2. Letter to Jill Lipoti, Ph D, New Jersey Department of Environmental Protection, dated September 16, 1999, concerns State of New Jersey soil cleanup standards and the opportunity to comment on the proposed New Jersey standards.

3. Letter to Olexander Smyshliaiev, Ministry of Environmental Protection and Nuclear Safety of Ukraine, dated September 14, 1999, concerns changes in the nuclear regulatory structure in Ukraine.

Federal Register Notices Issued

1. 10 CFR Parts 50 and 72; Changes, Tests, and Experiments; Final Rule.

2. Advisory Committee on Nuclear Waste; Notice of Meeting on October 12-13, 1999, in Las Vegas, Nevada.

3. Final Standard Review Plan on Foreign Ownership, Control, or Domination.

4. Advisory Committee on Reactor Safeguards; Procedures for Meetings.

5. Advisory Committee on Nuclear Waste; Procedures for Meetings.


Region I

[ Prev | Next ]

Unicom and PECO Energy Agree to Merger of Equals

Unicom Corporation (the parent of Commonwealth Edison Company) and PECO Energy Company announced on September 23, 1999, that they have entered into a merger agreement. The merger, which has been unanimously approved by both companies' boards of directors, will create a new holding company that will be the nation's largest electric utility, based on its approximately 5 million customers. The combined company will be the nation's fourth largest power generator, with generating power of more than 22,500 megawatts. Unicom currently owns 10 nuclear power plants; PECO owns 4.

Following the close of the merger, Corbin A. McNeill, Jr. (PECO) and John W. Rowe (Unicom) will become co-chief executive officers of the new holding company for a transition period lasting until December 31, 2003. At the end of the transition period, Mr. Rowe will become chairman and sole chief executive officer. Mr. McNeill will remain on the board of directors.

Misadministration at Holy Redeemer Hospital

On September 16, 1999, Region I was notified by Holy Redeemer Hospital and Medical Center, Meadowbrook, PA, of a medical misadministration. The patient's physician had intended that 300 microcuries of I-123 be administered for a thyroid uptake study. Instead, 5 milicuries of I-131, a therapeutic dose, were administered. I-131 is licensed by NRC, I-123 by the State. Two Region I inspectors were dispatched on September 17 to review the circumstances and evaluate the cause, licensee's actions to prevent recurrence, and the consequences of the event. Region I is contacting a medical consultant to obtain an additional evaluation of consequences to the patient. The Region is reviewing this event against the Abnormal Occurrence criteria and will continue to follow up on this case. The Commonwealth of Pennsylvania was informed of the misadministration.


Region II

[ Prev | Next ]

Incident Response Operations

On September 21, 1999, The Regional Administrator and other Region II staff met in RII with F. Congel and C. Miller, of Incident Response Operations, OEDO, to discuss interim procedures for agency event response and periodic meetings with state emergency responders.

Duke Power Company (Oconee Nuclear Station)

On September 21, 1999, Region II issued Oconee inspection report 99-12 which is the second in a series of inspections performed at Oconee to support the license renewal application review. The purpose of the inspection was to determine whether the Oconee aging management programs adequately support the license renewal application. Existing programs were found acceptable and documentation concerning future planned programs was consistent with the application.

Small Business and Civil Rights Meeting with All Managers & Supervisor

On September 23, 1999, Marva C. Gary, Civil Rights Program Manager, from the Office of Small Business and Civil Rights (SBCR) made a presentation to Region II managers. She met with all managers and supervisors to discuss the EEO complaint process and also to provide information about EEO resources that are available on the SBCR Home Page.


Region III

[ Prev | Next ]

Meeting with D.C. Cook Representatives

The Regional Administrator, the Director of the Office of Nuclear Reactor Regulation, and others of the Headquarters and Region III staffs met September 24, 1999, at NRC Headquarters with representatives of American Electric Power Co., operator of the D.C. Cook Nuclear Power Station. The Meeting was to review the status and Schedule for work underway at the D.C. Cook plant, which has been shut down since September 1997.


Region IV

[ Prev | Next ]

Public Meeting Between South Texas Project (STP) Nuclear Operating Company and NRC

On September 23, 1999, a public Meeting was held in the Region IV office with STP Nuclear Operating Company managers to discuss the status of the commitments related to a confirmatory order, dated June 8, 1998, modifying the STP operating license for STP. The licensee's plans for performing future comprehensive cultural assessments and annual "mini" surveys were discussed. This Meeting did not include the results of any previous surveys. Also included in this Meeting was the introduction of the new Director, Safety Quality Concerns Program at STP.


Office of Congressional Affairs

[ Prev | Next ]

Congressional Hearing Schedule, No. 35
OCA
Contact
Date
&
Place
Time Witness Subject Committee
Gerke TBA
SD-342
TBA Markup S. 59, S. 1244: Regulatory Reform bills Senators Thompson/Lieberman
Governmental Affairs
Gerke TBA TBA Markup H.R. 2445, Federalism Accountability Act Reps. Burton/Waxman
Government Reform
Keeling 09/28/99
SD-192
10:00 Sen. Lugar, State, DOD, DOE Y2K Readiness of Soviet-Designed Nuclear Reactors Senators Bennett/Dodd
Year 2000 Technology Problem
Rathbun 09/29/99
SD-406
9:30 Vote Confirmation of Richard Meserve Senators Chafee/Baucus
Environment and Public Works
Portner 09/29/99
SD-406
9:30 Markup S. 1627, NRC User Fees Senators Chafee/Baucus
Environment and Public Works
Portner 09/29/99
2123 RHOB
10:00 Markup H.R. 2531, NRC Authorization Reps. Bliley/Dingell
Commerce
Combs 10/19/99
TBA
TBA NRC, DOE Paducah GDP Senators Domenici/Reid
Energy and Water Development
Appropriations
SearchE-mailPhonebookNRC Home Page

Tool
bar
[Search | E-mail | Phonebook | NRC Home]


This page was last updated on October 1, 1999, by mailto:nrcweb@nrc.gov.